Project scope
This theatre is in 2003 equipped with 25 computerized elements. Winches are used to move pieces with SWLs of 300 kg and 600 kg. The maximum speed is 1.8 m/s. The control is through STS’s AutoStage2000 system. The controls are centrally located. The OptiMaster2000 desk, a precursor of ‘The Composer’ desk, is used with separate screens
In 2017 a new SIL3 flywall was installed with powerfly winches which can also be used as counterweighed assist in order to enlarge the SWL from 600 to 1000 kg.